The project to bring full fibre broadband to these areas (with download speeds of up to 900 Mbps) started on 8 July 2022 and was due to complete 12 months later – so it is now running a bit behind plan. However, it seems that the end is now in sight.

The following areas have been completed and enabled for full-fibre broadband; service can be ordered now:

  • Darvell Estate, Netherfield
  • Brightling Road east of Oxley’s Green
  • Premises between Coldharbour Farm and Pelham Bucks.

For the other areas, here is the latest status report from BT / Openreach. When it says “Expected completion” expect a further unpredictable period of time for “quality checks”. Any queries / comments, please email HighWealdsuperfastbroadband@gmail.com

PONIDNo. of premisesAreaStatus according to BT / Openreach
V800148Cackle Street, Darwell Hole areaBeing worked on and expecting them to be completed late July or early August.
V800941Woods CornerVirtually there now as well. Expected completion of 21/07/23
V900729Netherfield RoadInstallation complete.  Quality checks in progress at 11/07/23
V900838Perrymans Lane, Willingford Lane, Mount area, and road to Woods cornerBeing worked on and expecting them to be completed late July or early August.
V901051Central Brightling, Ox Lodge area and upper part of Cackle StBeing worked on and expecting them to be completed late July or early August.
V901246Darwell HillInstallation complete.  Quality checks in progress at 11/07/23