The project to bring full fibre broadband to these areas (with download speeds of up to 900 Mbps) started on 8 July 2022 and was due to complete 12 months later. Some parts have been completed; some have not, so obviously the project as a whole is somewhat behind plan.
Here is the latest status report from BT / Openreach. When it says “Expected completion” expect a further unpredictable period of time for “quality checks”. Any queries / comments, please email HighWealdsuperfastbroadband@gmail.com
PONID | No. of premises | Area | Status according to BT / Openreach |
V8001 | 48 | Cackle Street, Darwell Hole, Penhurst Lane area | Was previously expected to be complete late July or early August; no subsequent update from BT/Openreach |
V8009 | 41 | Woods Corner | Completion date now put back to 18 August, to be followed by quality checks (2 – 3 weeks?) before service is available to order |
V9007 | 29 | Netherfield Road | Live, available to order now! |
V9008 | 38 | Perrymans Lane, Willingford Lane, Mount area, and road to Woods corner | Was previously expected to be complete late July or early August; no subsequent update from BT/Openreach |
V9010 | 51 | Central Brightling, Ox Lodge area and upper part of Cackle St | Was previously expected to be complete late July or early August; no subsequent update from BT/Openreach |
V9012 | 46 | Darwell Hill | Live, available to order now! |